2014

DTE Energy/MichCon-Michigan
  • Anomaly Replacements 36", 30", 24"
  • Assist on Pigging 30", 10"
  • Launcher/Receiver Installation 30", 26", 24"
  • System Reliability Renewals (30,000)

Consumers Energy-Michigan
  • Meter and Regulator Station
  • Filter Separator Replacement
  • Compressor Station Pipe and Valve Replacements 26", 14", 12"

Panhandle Eastern Pipeline
  • Hydrotest 36"/30"-Illinois
  • Anomaly Repairs 26"-Indiana
  • Storage Field Modifications 20", 12", 6"-Michigan

Sun Pipeline
  • 6" Road Relocation-Ohio

Blue Water Gas Storage-Michigan
  • 4" Well Lateral
  • Station Rebuild (Measurement and Interconnect)
  • Hydrotest (3 Miles of 20")

Buckeye Pipeline-Michigan
  • 12" Anomaly Replacement

2013

DTE Energy/MichCon-Michigan
  • Anomaly Replacements 24"/12"
  • Station Upgrade 30"/24"
  • Integrity Replacements 30", 26", 24"
  • Assist on Pigging 30"
  • Service Mains
  • Main Replacement (1 Mile of 16")
  • System Reliability Upgrades
  • RCV Installations

Consumers Energy-Michigan
  • Install Launchers/Receivers 24"/20"
  • Meter and Regulation Stations
  • Valve Replacements 26"/20"
  • Anomaly Repairs 20"
  • 8" Storage Field Lateral

Sun Pipeline/Mid Valley
  • Meter and Pump Stations-Michigan
  • Pipe Replacement and Valve Replacement
  • 8" Relocation-Pennsylvania
  • 22" Road Bore-Ohio

East Tennessee Natural Gas
  • Meter Station and 1100' of 12"-Tennessee

Marathon Pipline
  • Anomaly Replacements (22")-Illinois
  • 30" Railroad Bore-Kentucky

Columbia Gas-Ohio
  • 2700' of 20"
  • Meter Station
  • 3 Miles of 12"

Panhandle Eastern-Michigan
  • Storage Field Modifications 20", 6", 4"

2012

DTE Energy/MichCon-Michigan
  • 10”/8” Road Crossings (HDD)
  • Casing Inspections
  • Assist on pigging operations 30”,24”,16”,12”
  • MLV replacements 24”,22”
  • Integrity work: 30”, 24” 20”, 16”, 12”
  • - Launchers/Receivers, MLV, Anomaly repairs and Direct Assessment

Spectra Energy
  • Hydrotest 12,000’ of 24” and relay 2,400’ of 24”-Ohio
  • Hydrotest 3,100’ of 24” and relay 260’ of 24”-Ohio

Marathon Pipeline Co.
  • Install 6,000’ of 16”: Michigan

Panhandle Eastern Pipe Line Co.
  • Storage Field Upgrade 20”, 12”, 6” 4”: Michigan
  • Drip Line Replacement 5,000’ of 4”: Michigan
  • Odorizer Station: Michigan

Sun Pipeline Co.
  • Relay 7,000’ of 6” (Conventional/HDD): Michigan

2011

DTE Energy/MichCon-Michigan
  • Assist pigging 36”, 30” 24”
  • City Gate Station
  • Slug Catcher Installation
  • 24”,30” MLV
  • Integrity work, 36”, 30”, 26”, 24”, 16”, 12”
  • - Anomaly repairs and Direct Assessment

Consumers Energy: Michigan
  • 36” Anomaly Repairs

Marathon Pipeline
  • 30” Bore: Kentucky

Panhandle Eastern Pipe Line Co.
  • 26” Road Replacements: Michigan, Ohio
  • Relay 1800’ of 20”: Michigan
  • 24” Drip Installation: Michigan
  • Filter Separator Installation: Michigan
  • Hydrotest 8 miles of 16”: Michigan

Sun Pipeline
  • Road Relocation 1,100’ of 22”: Ohio

2010

DTE Energy/MichCon-Michigan
  • Assist on pigging: 36”, 30”, 26”
  • Integrity work: 36”, 30”, 26”, 24” 16”
  • - Anomaly repairs, Launchers and Receivers and Testing

Consumers Energy: Michigan
  • Integrity Work: 36”, 30”, 26”, 16”, 12”
  • - Anomaly Repairs, Receiver and MLV, River Crossing, and City Gate Station.

2009

DTE Energy/MichCon: Michigan
  • Pipeline Rehab: 30” and 24”
  • Regulator/Gate Stations
  • Assist on Pigging 30”

Spectra Energy
  • Hydrotest 8,700’ of 24”: Ohio
  • Hydrotest 6,000’ of 24”: Indiana
  • Hydrotest 4,800’ of 24”: Indiana
  • 24” Replacement: Indiana

East Tennessee
  • Take up 6 miles of 12”, relay with 6 miles of 24” and station fabrication: Virginia

ANR Pipeline
  • Relay 4,500’ of 22”: Michigan

2008

DTE Energy/MichCon: Michigan
  • Pipeline Rehab: 24”

Spectra Energy
  • Relay 23,000’ of 30” Mississippi
  • Relay 4,700’ of 24”: Texas
  • Hydrotest 20,000’ of 24”: Arkansas
  • Hydrotest 3,500’ of 24”: Indiana

Fluor Corporation: Michigan
  • 24” and 30” Bores at the Marathon Refinery

2007

DTE Energy/MichCon: Michigan
  • Install 8 miles of 20” and Station Fabrication
  • Relay 4,500’ of 30”
  • Pipeline Rehab: 30”
  • Hydrotest 4 miles of 10”
  • Meter Stations
  • Casing Inspections

Spectra Energy
  • Relay 10,800’ of 36” and 30”: Kentucky
  • Hydrotest 8,000’ of 24”: Indiana
  • Hydrotest 4,500’ of 24”: Illinois
  • Hydrotest 5,600’ of 24”: Illinois

Severstal Steel: Michigan
  • Install 7,800’ of 16” and 14”